Thursday 23 August 2012

News report on tunneling effect

Tuesday 14 August 2012

Violation of MOU by Himagiri Hydro Energy Pvt. Ltd


As per the Article 4: Obligation of the Company, Clause 4.7 of the Memorandum of Understanding(MOU) signed between the company Himagiri Hydro Energy Pvt. Ltd and the Government of Sikkim, dated 5th December 2005, pertaining to Panang 280 MW HEP, the company is to achieve Financial Closure within 12 months from the date of signing of the agreement. It also states that in case of delay in obtaining Environment Clearance, the financial closure “shall have to be achieved within six months from the date of Environmental Clearance”. The company got the Environmental Clearance on 2nd January, 2007.
Even after six and half years of signing of MOU and four and half years of Environment Clearance the company has not achieved the Financial Closure. ACT confirms this on basis of information acquired through RTI.
As per the same Article and clause 4.9: (Equity participation) and clause 4.9.1, the State Government and the company are to execute the 26% equity subscription agreement (the public share) within six months from the signing of the MOU. But even after six and half years of signing of the MOU, the equity subscription agreement has not been executed.
This is a clear negligence and violation of one MOU. What about the other MOUs signed pertaining to mega hydro power projects in the state?
Through this press release, we would like to question and demand:
1.      Why these Articles and Clauses have not been adhered too?
2.      Why is the state government not taking serious action against the company for the violation of the MOU?
Hence we demand that the MOU be terminated as per Article 5, Clause 5.1 of the MOU for the interest of all and the environment and ecology of the state.



A team led by the International Rivers Network, South Asia Director, Samir Mehta made a field visit to Sikkim from the 10th-15 May 2012. The team consisted of office bearers from other organizations working on related issue from Kerala, Delhi, Manipur and North Bengal.
The main aim of the trip was to assess the ground situation of the hydro power project implementation and their fall outs and impact on the local environment, culture, demography etc along the main river of Sikkim, the Teesta and its tributaries. It was also to assess the future impact of water storage in Sikkim on the plains.
The team reached Sikkim on the evening of 9th May and halted for the night at the border town of Rangpo. The next day, along with the member of the local anti dam organization Affected Citizens of Teesta (ACT) left for Gangtok. On the way the team visited the project areas of Teesta Stage VI, 500 MW and Rongnichu 96 MW projects, where work is in progress.
From 11 to 14th the team spent the trip visiting the projects areas in the Lepcha-Bhutia tribal dominated North District of Sikkim, which also is targeted with the maximum numbers of HEPs in the state. The project areas of Teesta Stage V 510 MW, Teesta IV 520 MW HEP, 90 MW Dikchu HEP, 1200 MW Teesta Stage III, 99 MW Bop, 99 MW Bhimkyong, 99 MW Lachung and Panang 300 MW were visited during these four days.
Interaction with local people both directly and indirectly affected was carried out in these areas. The team halted for two days in the Chungthang town, which is the location of the 1200 MW Teesta III MW project dam, and which was the worst affected in the 18 September, 2011 earthquake. The last two days, 13 & 14 were spent in the indigenous Lepcha tribal reserve of Dzongu where Teesta IV and Panang HEPs are located. The most vociferous and sustained protest against these mega hydro projects has come from this area.
A brain storming session was held on the evening of the last day of the trip and various measures were discussed like matters to be taken up with the MOEF, CEA, indigenous people rights and legal possibilities related to specific projects and how to check and balance these haphazardly planned hydro project schemes in Sikkim. Each group was allotted their part of follow up work and responsibilities.

Thursday 21 June 2012

20th June' 2012.

ACT commemorated the 5th anniversary of the hunger strike protest against the hydro power projects in Dzongu by conducting a  token eight hours sit in dharna and reiterated their demand for cancellation of Panang 280 MW and Tessta Stage IV, 520 MW. At present works on both the projects are yet to start. The developers of  Panang HEP has been asked to submit geological and GLOF report by the Central Electricity Authority. It is yet to get clearance from the National Board of Wildlife as it is within 10 KM of Kanchenjunga National Park. Teesta Stage IV is still at preliminary stage.

Memorandum demanding the cancellation of the projects was submitted to the Chief Secretary of the Sikkim State Government. He will take up the matter soon. Further action will be decided upon the reaction to this memorandum.

Wednesday 26 October 2011

Chungthang town
A damaged building in Chungthang town, which is near the dam site of Teesta III
Defaced hill opposite Teesta III dam site. The construction activities and use of explosives had kept them ready for the quake to give the final touch.
Dam Site Teesta Stage III, 1200 MW
Adit II complex
Between Adit III & II
Adit IV area
The construction activities and the dynamites had kept it all ready for the earth quake to give the final shake downThe Adit V and surge shaft area of Teesta III, 1200 MW HEP after the 18th September earthquake

Thursday 17 March 2011






On the 14th March,2011, the International day of Action for Rivers, ACT volunteers pledged their allegiance to the river Teesta and vowed to fight to defend it, on the spot where the dam of Teesta Stage IV 520 MW hydro project is planned. If the dam is built, the last free flowing stretch of Teesta river, will be put into tunnel and the entire river Teesta, will disappear forever into tunnels.


Friday 21 January 2011

Do we need that bridge?
A part of river Teesta downstream of the Teesta Stage V 510 MW hydro project dam

Wednesday 10 November 2010

Temacapulin we are with you

ACT members in solidarity with Temacapulin

Tuesday 2 November 2010

ACT participates in the 3rd International Rivers Meet in Mexico



South Asian Delegates







With Maria Guadalupe Lara Lara who fought the Arciediano dam successfully

International dam affected communities, civil organizations and activists met at the 3rd International Rivers Meet at Temacapulin, Guadalajara-Mexico from the 1st to 7th October 2010 under the umbrella organization the International Rivers Network (IRN) Chaired by its Executive Director Mr. Patrick Macully.
The Indian delegates were led by the International Rivers South Asian Director Mr. Samir Mehta. Affected Citizens of Teesta (ACT) was represented by General Secretary Dawa Lepcha.
The seven days meeting was attended by participants from 56 countries from all the continents. The sessions and workshops dwelled on the dams, displacement, networking, support, exchange of ideas and experiences. The meeting also expressed and displayed solidarity to the host village Temacapulin which is facing submergence threat from El Zapatillo dam being built on the Rio Verde.
Field trips were also conducted to nearby dam sites which were being opposed by the local people. One such trip was the visit to the successfully fought Arcediano dam where one single woman, Maria Guadlupe Lara and her family stood their ground (after others had given up). With their homestead bulldozed and razed to the ground and the odds heavy against them she fought on with the help and support of civil societies and international support and finally won her battle after nine years.
All delegates pledged to continue with the struggle against unjust and absurd developmental programmes and support each other in their struggle. The meeting ended with endorsement of The Declaration of Temaca in which solidarity, achievements, challenges, demands and commitments were declared. More information on http://www.internationalrivers.org/

Water For life, Not For Death!
Free Rivers, For Free People!

Sunday 20 June 2010






ACT commemorates its Satyagraha on 20th June 2010 by offering ceremonial scarfs/'khadas' on the Mahatma Gandhi bust on the main mall of Gangtok and by planting saplings nearby Gangtok.

Monday 12 April 2010

CAG REPORT 2010 ON THE HYDEL PROJECTS IN SIKKIM - Part 1

The CAG in its 2008-09 report published recently has recommended the State Government to strengthen the monitoring and vigil aspects of the hydle power projects execution by the Independent Power Projects (IPPs).

“Monitoring of execution of projects was virtually non-existent”, said CAG after reviewing the performance of the hydle power thrust of the State government.

The State Government displayed no serious intention to act on the agreement inked with IPPs to have multi- disciplinary committee to monitor the various issues arising during the implementation of the projects, the CAG said. The clause in the agreement regarding constitution of the committee for monitoring the projects was included only on paper, said the CGA.

The CAG further indicated laxity on part of Sikkim Power Development Corporation (SPDC) in monitoring implementation OF THE WELFARE ACTIVITIES IN THE PROJECT AREAS.

“The SPDC was categorically asked to provide details of constitution of the Project Level Welfare Committees for each project with the details of members, minutes of meetings of the committees, reports of committees and the Welfare activities undertaken. No such details could be provided to audit”, said the CAG.

The CAG also pointed out the absence of any mechanism to regularly monitor execution of projects and keep a constant vigil to see if any objects of value were unearthed during the course of execution of implementation.”There was thus , no deterrent in the existing system to prevent the developers or any of their employee/contractor from pilfering any precious materials that may be unearthed during the execution of the projects”, it said.

The report also exposes the lack of adequate experience among the SPDC officers in planning and execution of mega hydro power projects as detailed project of the mini projects of 1 to 2 MW capacity executed by the SPDC were prepared and vetted by either the IIT’s or the Technical Institutions of the Country.

Despite these facts, the technical soundness and economic viability of all projects below 100 MW (total 13 projects) awarded to IPPs were cleared by the SPDC for execution , the CAG said. This was the fraught with the risk of future non-performance , underperformance and non-viability , the CAG said.
The CAG also rejected the reply of the department as no evidence was furnished to substantiate the department’s claim.

CAG REPORT 2010 ON THE HYDEL PROJECTS IN SIKKIM - Part 2

While hundreds of crores of rupees in potential hydel power revenue washed down the rivers here due to an amateurish hydel policy on the part of the State government, the rich aquatic life in the Hilly State has also been hit hard by failure on the part of government and power developers.

In the report, the CAG highlighted the necessity to make adequate provisions in the environment plans for undesigning suitable measures to migrate the effect of hydel power projects on aquatic life of Sikkim. There are 63 species of Phytoplankton, 17 species of Zoo Phytoplankton and 48 species of fish inhabiting the river systems of Sikkim.

The creation of reservoirs, fluctuation in natural river discharge and diversion of river waters through closed tunnels would completely change the ecological conditions of the river systems.

“MoUs were needed to be signed with the project developers securing their commitments for a long term comphrensive strategy for preservation and protection of fishes and aquatic life in the river systems of the State”, the CAG said.

While in ten projects, the preservation measures were mainly alternative strategies which defeated the whole idea, the CAG pointed out that no provisions were made in the environment management plan of Chujachen and Bhasmey projects.

Teesta State V Project commissioned on March, 2008 has failed too on this count. About 23 Kms of Teesta river between the dam site and tail end of this project was direct through tunnels in the projects.

“The fish species and other aquatic organisms along with stretch of rive thus already suffered possible damages due to the changes in the flow of water”, the CAG said in a report.

The CAG also said that the catchment area treatment plant for the power projects were prepared without taking into account the field requirement for survival of the plantations and were therefore , aribitary and inadequate . It also rejected the reply of the State Forest Department on the issue accussing the department of not ensuring adherence to the plans to the prevalent norms.

The CAG also placed that the environment management plans for the projects had been prepared through assessment of secondary data without diligent study, observation and research of prevailing ground realities ove ran adequate period of time.

The State Pollution Control Board (SPCB) jas also been found wanting by CAG for failing to identify specific locations for dumping excavated materials from the project sites. Thus there was indiscriminate disposal of muck by the developers causing degradation of land, air and water, it said.

The CAG has provided the finding of the State Mines and Minerals Department which reveals gross negligence by NHPC in disposal of muck generated from the execution of Teesta State V project. Spoils were thrown along the river banks raising the river bed of the Teesta leading to change in flood behaviour of the river , acceleration of toe erosion and degradation of the overall geo-environmental setting in the area, the report said.

“In case of another project (Panan HEP), the sites identified for disposal of much was too small to retain safely the huge quantity of muck which could lead to future disaster such as enhanced siltation of reservoirs if the downstream projects, toe erosion and change in the geo-environmental setting of the downstream areas”, said in a CAG report.

CAG REPORTS 2010 - undue favoritism to Gati Infrastructure


The CAG has censured the State Government for showing undue favoritism while awarding three hydro power projects to GATI Infrastructure Ltd (GIL) which led to losses in crores of rupees to the State Exchequer.

The Agreement with the GIL for the award of three projects were unduly skewed in favour of GIL thereby resulting outright losses of Rs 22.17 lakhs towards the processing fees, unnecessary loan liability of Rs 3.68 crores (puls interest) borrowed from road construction, loss of Rs 21.7 lakhs per year on penalty in the event of delay in commissioning the projects, loss of Rs 1.32 crores per year towards environmental cess and loss of Rs 17 lakhs incurred by the SPDC on investigation studies for the three projects, the CAG said.

The State Government had signed an agreement with GIL on November 2003 for development of three hydro power projects in Sikkim-Sada Mangder (63 MW), Chujachen (57 MW) and Bhasmey (32 MW). The installed capacities of these projects were later enhanced to 71 MW, 99 MW and 51.7 MW respectively.

Later, the State Government signed 18 agreements with other developers between July 2005 and December 2008 for developing hydro power projects. In these agreements, the State Government imposed wide range offing conditions including processing fees and penalty charges.

None of the above conditions were imposed on GIL, the CAG said th. Besides, the State Government expressly agreed to provide access roads to all the three projects sites of GIL at its own costs and entered into a loan agreement with GIL through the Sikkim Power Development Corporation for availing loan of Rs 4.2 crores to be utilized for construction of approach road to power house for its Chujachen project, said.

In response, the department informed that certain extra incentives were given to GIL with a view to attract other developers as it was the first independent power producer (IPP) to venture in the State.

“The reply was not acceptable as the discrepancy was due to non-existence of hydro power policy and absence of any standard terms, conditions and criteria of the projects to IPPs”, the CAG said.

HYDRO POWER PROJECTS WERE AWARDED AT THROWAWAY CHARGES : CAG

HYDRO POWER PROJECTS WERE AWARDED AT THROWAWAY CHARGES : CAG

‘Astronomical loss in potential revenue due to absence of defined hydel policy’

The white paper tabled in the Assembly in July last year had indicated that the State Government itself of taking a ‘piecemeal approach’ while unleashing ‘bolt from the blue’ to the clueless Sikkimese people on the hydel thrust, the CAG has translated this ‘institutional failure’ into a financial haemorrhage , the quantum of which runs into hundreds of crores of rupees at the cost of the exchequer-all due to ‘absence of firm and defined policy’.

In its report for the year ended 31 March 2009 which was tabled in Sikkim Legislative Assembly today, the CAG said that the State had neither finalized its hydro power policy nor prepared a time bound plan till date for the implementation of 35 hydel power projects indentified with an aggregate installed capacity of 5,741.2 MW in Sikkim.

Barring Rangeet Stage III (60 MW) and Teesta Stage V (510 MW) which had been commissioned already , thirteen power projects are at various stages of process while 8 projects are yet to make any progress as of September 2009, the CAG said.

“Absence of a firm and defined policy and a definite plan led to inconsistency in awards of projects and lack of well thought revenue model resulted in loss of potential revenue”, said the CAG in its report questioning transparency in award of the power projects.

Open advertisement and dissemination of information was not done and instead all the projects, irrespective of the size were awarded by the State Government through the MoU route without calling for bids, the CAG sobserved.

“Despite considerable hue and cry in the State regarding the methodology adopted for the award of the projects, the Government has not notified the details of potential available, modality for the award of projects, technical capability, financial strength and experience of IPPs (Independent Power Producers) chosen etc to the public”, the CAG said.

Wednesday 10 March 2010




In spite of strict specific clearance condition from the MOEF that no labour or staff colony should be set up in the Dzongu Lepcha reserve, Himagiri Hydro Energy Private Limited has bought land for setting up colony in Lingzya (dam site of Panan 280 MW HEP)Dzongu, in blatant violation of the environment clearance condition.